MEMORANDUM
TO: City Council
FROM: David J. Deutsch, City Manager
SUBJECT: City Transportation Priority List for 2003-2004
DATE: July 30, 2003
I. Background
Each year, the City Council conducts an overview of the State’s Consolidated Transportation Program (CTP) and County Capital Improvement Program (CIP) for the purposes of establishing the City’s Transportation Priority Listing. The City’s priorities are communicated to State and County officials as early input to the next year’s budget cycle.
A typical project in the CTP will go through four distinct stages (as noted below). Not all activities for each project may be funded at the same time. Some projects are funded for the first activity, but then left dormant for various reasons. The levels of activity, or stages, a typical project goes through are:
· Project Planning, which is a two-step process. The first part of
Project Planning is the delineation of a project’s limits and identification
of those agencies whose participation will be necessary in the project. The
second step is to determine necessary improvements which may be required
for construction of a project, such as identifying various activities like
right-of-way acquisition or wetlands mitigation which must be carried out,
and determining such design aspects of a project as the required number of
lanes or whether noise barriers will be required;
· Design and Engineering, which is where the actual details of such factors
as how much fill may be needed, where the various utilities will be located
(i.e., underground versus overhead), etc., are determined;
· Right-of-Way Acquisition, which is where SHA actually negotiates with
land owners to obtain whatever land is needed to construct the project; and
· Construction, which is the final activity where the road or improvement
is actually constructed.
It should be noted that some of the four stages of a project can occur simultaneously. It is not uncommon for planning and engineering, planning and right-of-way acquisition, engineering and right-of-way acquisition, or in some cases, construction and right-of-way acquisition to take place at the same time. For very large projects, phasing is also common, with different action taking place in the different phases.
II. State Transportation Projects
Attachment #1 is the City’s priority list for State transportation projects. These projects are summarized below by category:
A. Construction Projects
1. MD 450, from MD 193 to Stonybrook Drive (Line 9)
2. US Route 50 HOV lanes (Line 5)
B. Right-of-Way Acquisition Projects
1. US 301/MD 197 interchange (Line 24)
2. US 301 South Corridor (Line 23)
C. Design and Engineering Projects
1. MD 450 from Stonybrook Drive to west of MD 3 (Line 28)
D. Project Planning
1. US 301/MD 197 interchange (Line 24)
2. MD 3, from MD 450 to Anne Arundel County line (Line 18)
3. US 301 South Corridor (Line 23)
Recommendation:
Consistent with past policy, the City should continue to support the projects shown in the CTP, as well as the following actions:
1. Move MD 450 from Stonybrook Drive to west of MD 3 from Design and Engineering
to Construction Projects and revise project description to include a pedestrian
bridge over MD 450.
2. Move US 301/197 interchange from Planning to Design and Engineering Projects.
3. Move MD 3 from MD 450 to Anne Arundel County line from Project Planning
to Design and Engineering Projects.
4. Add a new project, MD 197 from Kenhill Drive to MD 450, to Project Planning.
5. Add a new project, US Route 50 interchange between MD 704 and MD 197 to
Project Planning.
6. Add a new project, US Route 50 Trumpet Interchange at the Maryland Science
and Technology Center (MSTC) to Project Planning.
The letter sent to the State also included numerous projects described as “Other SHA Projects”. These are projects that address safety issues and/or enhance the appearance and accessibility of the transportation system, including:
1. Cameras at traffic signals
2. Opticon devices
3. MD 197 North Median, from MD 450 north to Rockledge Elementary School
4. MD 197 South Median, from US 50 to US 301
5. WB & A Bridge over the Patuxent River
6. Old Town Bowie/MD 564 traffic safety improvements
7. Sidewalks along 11th Street (MD 564) in Old Town Bowie
8. Deceleration lanes on MD 197 at Holiday Lane and on MD 214 at Danfield
Drive
9. Lengthening the northbound left-turn lane on US 301 at Mitchellville Road
10. Sight distance improvements at MD 214/Jennings Mill Drive intersection
Efforts to implement technological improvements, such as cameras and Opticon devices, are ongoing. A general community consensus was previously achieved on both Route 197 Median landscaping projects. These projects are awaiting State funding through the Neighborhood Conservation Program, which is currently on hold due to budget constraints. The HOV lanes were opened on US 50 last year; the portion of the project involving erection of noise walls at the Princeton Square development is currently under construction. Support for a new bridge over the Patuxent River for the WB & A continues, as staff works with local trail groups, including those from Anne Arundel County. Completion of this connection was recently recommended in the Citywide Trails Plan. Improvements in Old Town Bowie, including traffic safety in the vicinity of the railroad bridge have been the focus of the Old Town Committee, which has reviewed various roadway design alternatives. Coordination of the sidewalk installation program in Old Town is being achieved through the City’s Community Development Block Grant (CDBG) program. Due to funding constraints, several of the other District 3 projects, such as those involving deceleration lanes and turn lanes, have been put on hold. At the City’s request, the State did recently provide protected left-turn phases at the MD 214 intersections with Church Road and Jennings Mill Drive.
Recommendation: It is recommended that the City Council reiterate its support for the projects contained in the October 2002 letter to the Transportation Secretary.
III. County Transportation Projects
Attachment #2 identifies County transportation projects, as they appear in the County CIP. Note that “design and engineering” and “planning” categories are combined for County CIP projects. The County projects in the Bowie area are summarized below by category:
A. Construction Projects
1. Collington Branch Stream Valley Trail
2. Bridge Replacement – Race Track Road
3. Mitchellville Road
4. US Route 301 improvements (south of MD 214)
B. Right-of-Way Acquisition
1. Governor Bridge Road
C. Planning Projects (including Design and Engineering Projects)
1. High Bridge Road
2. Mount Oak Road
3. Woodmore Road
Recommendation:
There are numerous projects described in the City’s letter from last year that are not included in the County’s CIP document (e.g. Church Road). Staff is recommending that these be included again in the City letter. Consistent with past policy, the City should support the projects shown in the CIP, with the changes and additions noted below:
1. Pursuant to the adopted Citywide Trails Plan, request redirection of construction funding for the Collington Branch Stream Valley Trail to construction of trail segments using the A-44 right-of-way. The revised project is recommended for the Construction Projects category.
2. Add a Hiker-Biker Trail Project along Old Chapel Road and Race Track Road to Construction Projects.
3. Move both the Mount Oak Road and Woodmore Road projects to Construction Projects.
4. Add Church Road from Leeland Road to MD 450, including signalization at Mount Oak Road, to Right-of-Way Acquisition Projects, including funding for planning, design and engineering.
5. Add a Hiker-Biker Trail Project along Chestnut Avenue linking Old Town Bowie and the proposed High Bridge Road improvement project, which terminates at Fletchertown Road, to Planning Projects.
6. Add a project to replace the existing bridge over the Patuxent River
on Governor Bridge Road to Planning Projects.
7. Add a project to construct a new pedestrian bridge over MD 214 in accordance
with the Citywide Trails Plan to Planning Projects.
Attachment 1: Detailed Description of Projects
State CTP Projects
Construction Projects
1. MD Route 450 from MD 193 to Stonybrook Drive
(Prince George’s County
Line 9) - (Under Construction) This project consists of the construction
of a divided road with four through-lanes and varying numbers of turn lanes
to serve the intersections with the various streets along this segment. Included
in this project is a very substantial landscaping plan which features both
shade and ornamental trees, shrubbery, seasonal flora, and use of brick in
the design of medians. Crosswalks and other pedestrian areas will be given
special treatment to make drivers aware that they are approaching a special
location.
2. US Route 50 HOV Lanes (Prince George’s County Line 5) – (Under
Construction) This project involves the construction of High Occupancy Volume
(HOV) lanes on US Route 50 between the US Route 50/MD Route 3 interchange
and a point approximately one mile west of the Capital Beltway. Construction
of noise barriers from I-495 to west of US Route 50/ MD Route 197 for the
Princeton Square community is part of the project, as well as an extension
of the acceleration lane onto Route 50 from Route 197.
Right-of-Way Acquisition Projects
1. US Route 301/MD Route 197 interchange (Prince George’s County Line
24) – Study to upgrade and widen US Route 301, from north of Mount
Oak Road to US 50 (2.0 miles) and MD 197 from US 301 to Mitchellville Road
(0.3 miles). Shoulders will accommodate bicycles. Sidewalks will be provided
where appropriate. Improvements are needed to accommodate the existing and
projected high volumes of traffic generated by continuing growth along the
US 301 corridor and to address existing safety problems. Some planning and
right-of-way funds were deleted due to the national economic slowdown.
2. US Route 301 South Corridor Transportation Study (Prince George’s
County Line 23) - This is a multi-modal corridor study to consider highway/transit
improvements south of La Plata to US Routes 301/50 interchange in Bowie,
and to Branch Avenue Metro Station. The study includes preparing the appropriate
environmental approvals for recommended alternatives. The study is being
coordinated with other studies to identify short/long range transit alternatives.
Bicycle and pedestrian access will be included in the study. Some planning
and right-of-way funds were deleted due to the national economic slowdown.
Design and Engineering Projects
1. Route 450 from Stonybrook Drive to MD Route 3 (Line 28) - This project consists of design and engineering to upgrade the section of MD Route 450 from a point approximately 1,000 feet east of its intersection with Stonybrook Drive to MD Route 3 to a divided highway with four through lanes of traffic. Planning studies were completed for this segment in 1988.
Project Planning
1. US Route 301/ MD Route 197 Interchange (Line 24) - Study to upgrade and
widen US Route 301, from north of Mount Oak Road to US 50 (2.0 miles) and
MD 197 from US 301 to Mitchellville Road (0.3 miles). Shoulders will accommodate
bicycles. Sidewalks will be provided where appropriate. Improvements are
needed to accommodate the existing and projected high volumes of traffic
generated by continuing growth along the US 301 corridor and to address existing
safety problems. Some planning and right-of-way funds were deleted due to
the national economic slowdown.
2. MD Route 3 (Line 18) - This project consists of a study to upgrade MD
Route 3 from US Route 50 to MD Route 32 (8.89 miles) to address safety and
capacity concerns. The project would improve safety and relieve traffic congestion
in this heavily traveled corridor. In 2000, the annual average daily traffic
was 67,900, and it is projected to be 106,250 in the year 2025.
3. US Route 301 Corridor Transportation Study (Line 23) - This is a multi-modal
corridor study to consider highway/transit improvements south of La Plata
to US Routes 301/50 interchange in Bowie, and to Branch Avenue Metro Station.
The study includes preparing the appropriate environmental approvals for
recommended alternatives. The study is being coordinated with other studies
to identify short/long range transit alternatives. Bicycle and pedestrian
access will be included in the study. Some planning and right-of-way funds
were deleted due to the national economic slowdown.
County CIP Projects
Construction Projects
1. Collington Branch Stream Valley Trail - The project involves the construction
of a hiker-biker trail from US Route 50 southward toward Central Avenue (MD
Route 214). This is an important trail system essential to complement the
north-south trail network serving the City. This trail is in conformance
with the County-wide Trail Master Plan and is already in the County Capital
Improvement Program (CIP). The trail also represents a coordinated effort
with the State Highway Administration to provide a connection under US Route
50/MD Route 197 overpass.
2. Bridge Replacement – Race Track Road – This project consists
of the replacement of the existing Race Track Road Bridge over Horsepen
Branch. The bridge was originally constructed in 1945 and reconstructed
in 1950.
3. Mitchellville Road – This project consists of the reconstruction
of the existing roadway from MD 197 to Mount Oak Road, as a four/six lane
urban divided highway including a sidewalk on the west side and a bike
path on the east side. Improvements include paving the shoulders and resurfacing
the roadway from US 301 to Mount Oak Road. This project also incorporates
minor geometric improvements at the US 301 interesection, including landscaping.
Project completion is anticipated by June, 2003.
4. US Route 301 Improvements (south of MD 214) – This project is
necessary to provide satisfactory levels of service during peak periods
at intersections and along US 301, should SHA planned improvements be delayed.
Funding is primarily through developer contributions.
Right-of-Way Acquisition Projects
1. Governor Bridge Road – Reconstruction of the existing road to a multi-lane urban roadway in the vicinity of US Route 301 and as a two-lane rural roadway with paved shoulders from that point to the Anne Arundel County line. The existing roadway is narrow and does not meet current and projected traffic demands. Increased traffic volumes have resulted from development in the area.
Design/Engineering and Planning Projects
1. High Bridge Road – This project will consist of a two-lane urban
reconstruction from MD 450 to Fletchertown Road. The project will provide
drainage improvements and improve pedestrian movement as well as provide
access to the WB & A trail. The existing roadway is narrow, has drainage
problems and does not provide for pedestrian and bicyclist movements.
2. Mount Oak Road – This project will provide for a multi-lane reconstruction
of the existing roadway from Church Road to Mitchellville Road in accordance
with the area master plan. The design of the project will include an evaluation
of the need to construct a bridge overt the Conrail railroad tracks. The
existing roadway requires capacity, alignment and drainage improvements.
Rapid development in the area is causing an increase in traffic volumes,
necessitating capacity improvements.
3. Woodmore Road – This project will consist of the complete dualization
of Woodmore Road from east of MD 193 to Church Road. The project will include
the reconstruction of the existing westbound roadway, where appropriate,
to meet current design standards. A minor relocation at Church Roadwill
also be considered to provide a common intersection with Mount Oak Road.
The existing roadway is substandard and will not satisfy the projected
needs of the adjoining developing area and anticipated increases in through
trips. This project will provide a much needed additional east-west connection
from South Bowie to Largo and the Capital Beltway.