Indoor Sports Facility

Status of This Project 

Plans for the Indoor Sports Facility have evolved since the concept was first introduced several years ago. Current plans are for the City of Bowie to build a large indoor sports facility on a parcel of land on Church Road that the City purchased from the Maryland-National Park and Planning Commission. 

Features


The facility will include:
  • Five (5) hardwood basketball courts, much like those found at the Bowie Gymnasium
  • Six volleyball courts (overlaying the basketball courts)
  • Two (2) sheets of ice - one Olympic size and the other NHL size
  • Support spaces and meeting rooms
  • Outside parking for 525 vehicles

Location


A parcel of land on Church Road purchased from the Maryland-National Capital Park and Planning Commission.

Anticipated Project Timetable


  • Design Complete: February 2018 
  • Building Permits Obtained: September 2018 
  • Construction Contractor Hired: September 2018 
  • Construction Complete: March 2020

Project Costs


The updated total project costs are estimated at $28 million. Funding for the project will come from General Fund revenues and from the issuance of bonds.

Public Engagement


The City’s architect will be hosting sessions to engage Bowie residents on their design.  Information on these opportunities will be posted in the near future.  


Project Milestones to Date


City Council has been actively involved in the decision making for this project since hiring a consultant to complete a feasibility study for the facility in 2013. Below are the project milestones to date:

June 3, 2013 – Sports Facilities Advisory (SFA) presented a report to City Council at a public hearing showing their analysis of the need for a court facility, an ice facility, an aquatic facility and a turf facility in the City of Bowie. The SFA analysis also provided construction cost estimates and operating cost estimates for each of these types of facilities. Finally the SFA report provided recommendations regarding the scope of improvements for each of the above activities. The City had engaged the services of SFA to provide the above analysis. 

May 13, 2014 – A special Council Worksession was held concerning constructing an Indoor Sports Facility looking at five options as designated by City Council as follows: 
a) no build;
b) construction of a replacement ice facility only; 
c) construction of a court facility only;
d) construction of a court facility and construction of an ice facility; and 
e) construction of a replacement ice facility followed by construction of a court facility. 
Cost information, using the SFA analysis, was presented and timelines developed for each option. The time lines were established using the time frame for the City Hall Project as an example.

May 19, 2014 – City Council adopted a budget CIP for FY 2015 that included the recommendation to construct a court facility and an ice facility. Specifications for the court and ice facility were as recommended in the SFA analysis. Budgeted costs were based on those established by SFA. 

May 18, 2015 – City Council adopted a budget for FY 2016 that again included the recommendation to construct a court facility and ice facility using the same information as contained in the FY 2015 budget. The reason this was done is that the City was unable to locate a property that was sufficient to begin this project in FY 2015. 

May 16, 2016 – City Council adopted a budget for FY 2017 that once again included the recommendation to construct a court facility and ice facility using the same information as contained in the FY 2015 budget. Again, the reason this was done is that the City was unable to locate a property that was sufficient to begin this project in FY 2016. 

The process for selecting a site for the facility was extensive. Using the City's GIS system, undeveloped parcels of land that were in close proximity to central Bowie and of sufficient size were identified. In the end, a 20-acre parcel off of Church Road (northeast of Freeway Airport) was selected as the best location. In 2015 a site analysis was conducted and negotiations began with the owner (Maryland National Capital Park & Planning Commission). The property was acquired by the City in the spring of 2016. 

June 23, 2016 – The deed was recorded on the acquisition of the Church Road property with M-NCPPC to acquire a 20-acre site for $210,000 on which to construct the Indoor Sports Facility. 

September 6, 2016 - At a City Council meeting, the Council voted to hire a project management firm for this project. View staff report for this meeting.

February 21, 2017 - At a City Council meeting, the Council voted to hire the project architect, Hughes Group Architects, of Germantown, MD. 

March 15, 2017 – City staff met with the Architect to kick-off the design process. 

Documents Related to the Indoor Sports Facility Study (2013)